Leeuwarden, skidding 5 bridges and tunnels

General information


For the big highway project ‘Hook around Leeuwarden’ CTdeBoer skidded 5 bridges and tunnels at the new-build western highway.


Involved parties


– Client: ProRail

– General contractor: Grutte Fier (Mobilis, Oosterhof Holman, Van Gelder, J.J. de Vries)


Numbers/ technique used:


1st weekend closure: railway deck KW7: 1750 tons skidded 28m on 4 axes


1st weekend closure: railway tunnel KW20 North: 1800 tons skidded 51m under a 4% slope downwards


2nd weekend closure: railway deck KW5: 900 tons skidded 24m on 3 axes


2nd weekend closure: railway deck KW19: 1350 tons skidded 24m on 4 axes


2nd weekend closure: railway tunnel KW20 South: 1600 tons skidded 44m under a 4% slope downwards


 


Period


June – August 2013

1st weekend closure: 12, 13 and 14th of July 2013


2nd weekend closure: 23, 24 and 25th of August 2013